Project Snapshot (at a glance):
Pipe Installed:
16-inch steel transmission & MDPE (various sizes)
Key Work Elements:
Utility relocation, valve repair, regulator stations
Environment:
Mixed utility corridor
Primary Goal:
Completing and integrating partially finished infrastructure
Project Highlight:
The Mitchell Point project was initially started by another contractor, and Ross & Sons was brought in to complete the remaining work. Our team performed utility crossing relocation, valve repair, and the installation of multiple sections of 16-inch steel transmission pipeline. In addition, we installed various sizes of MDPE pipe and set regulator stations to ensure the system was properly integrated. The project was completed efficiently, resulting in a seamless transition and fully functional transmission and distribution infrastructure.